Milestones

Milestone numberMilestone nameRelated work package(s)Due date (in month)Means of verification
M1Project kick-off meeting heldallM3Meeting held
M2Data Committee established5M3First meeting held
M3Stakeholder group recruited3M6First meeting of the full group held
M4New instrumentation installed in Belgrade and data flow established1,2M8First data available
M5Training for field campaigns completed1M10Event held
M6First field campaign started2M12Progress report M12
M7Chemical and biological characterization of collected samples started2M18Data available
M8Data archive compliant with data management plan established2,5M18Data archive available for data inputs
M9At least two ICLs held1,2M24Results available
M10Training for PMF completed1M24One scientist trained
M11Chemical and biological characterization of samples completed2, 3M26Data available for analysis