Milestone number | Milestone name | Related work package(s) | Due date (in month) | Means of verification |
M1 | Project kick-off meeting held | all | M3 | Meeting held |
M2 | Data Committee established | 5 | M3 | First meeting held |
M3 | Stakeholder group recruited | 3 | M6 | First meeting of the full group held |
M4 | New instrumentation installed in Belgrade and data flow established | 1,2 | M8 | First data available |
M5 | Training for field campaigns completed | 1 | M10 | Event held |
M6 | First field campaign started | 2 | M12 | Progress report M12 |
M7 | Chemical and biological characterization of collected samples started | 2 | M18 | Data available |
M8 | Data archive compliant with data management plan established | 2,5 | M18 | Data archive available for data inputs |
M9 | At least two ICLs held | 1,2 | M24 | Results available |
M10 | Training for PMF completed | 1 | M24 | One scientist trained |
M11 | Chemical and biological characterization of samples completed | 2, 3 | M26 | Data available for analysis |